REFINERY PROJECT

Member for

17 years 5 months

It all goes about money.



How fast can you spend it.



To Spend 17 M in 18 Months is a slow project.



I Have been on Project.



1.8 B 36 Month (Engineering had to be done in 5 country’s / Fabrication in another & Construction in another



100 M 7 Month All in One Country



360 M 12 Months All In One Country



25 M = 8 Months all in One Country.



Some times it is not possible to spend money fast enough.





So to answer it quickly if a Project Duration is 20 Month 3 to 7 % per Month



If it is 10 Month 7 to 14 % per Months










Member for

22 years

Ian Thanks.



These figures gave me a good idea.



Jorge

Member for

22 years 1 month

What sort of project? T/A involvement. No T/A Involvement

Our major project worth 17 Million US dollars with no turnaround involved took 18 months.



8 months to 10% design mainly, 11 months to 20%, then almost 10% a month to completion. Does that help?