I also encountered the same issue, but when I tried to select the “Hide if empty” check box under the “Group and Sort” tab all the date(month) which is empty will not be included when I paste it to excel sheet. It will only copy the PS and PF date of the project.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2017-06-08 13:08
I am facing a similar issue. on the assigment view, I have done the grouping by Resource name and then WBS. I have checked "Show Grand Totals" in Display options. After I selecting this view (Ctrl+A) when I try to copy (Ctrl+C), the Total, Resource name and WBS are getting de-selected and I cannot copy/paste that to excel sheet. I tried this with changing the grouping to Resource ID name, still facing same issue. What is the cause of this issue and what is the solution?
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2016-03-23 12:06
I had the same problem occured to me as well. F5 Refresh command did not work for me.
However, changing the levels in Grouing to 'Resource ID Name (Levels ...)' solved the problem of copying and pasting directly from P6. Now I can use my Ctrl+C. Hope it helps.
I had the same problem occured to me as well. F5 Refresh command did not work for me.
However, changing the levels in Grouing to 'Resource ID Name (Levels ...)' solved the problem of copying and pasting directly from P6. Now I can use my Ctrl+C. Hope it helps.
Regards,
Talgat Baimukanov
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2015-10-21 13:37
I already made that what you had explained but still the same I cannot extract the exact data I wanted to get.I am using now report wizard which will take time.I was still hoping that you can provide more another options.
Hello Robin,
Pressing F5 or refreshin the program still didn't work out.Doing report wizard was my last option as of now that is taking time.Hope you can provide more options.
Thanks
Member for
15 years 2 months
Member for15 years2 months
Submitted by Robin Clare-Talbot on Mon, 2015-10-19 05:33
This is a very common issue, and has to do primarily with hardware constraints. If you are copying from the resource assignments table to excel for s-curves etc, sometimes it does not allow you to select the entire range.
Quite simple, hit F5 to refresh data, this should most of the time work, and then you can re-select all the data, alternatively restart your P6.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2015-10-09 13:24
I do not know what you mean by setting the time scale. All you do is highlight the values you want from when want to start to copy them to when you want to finish copying them.
Select the first month and data press the shift and control key now go to the right and select the last month of your data
leave go of the shift key and the control key and press control-v
I face the same problem with this one and it will be much more help if you can give more detailed sequence in timeframe settings with filter activities.
I face the same problem with this one and it will be much more help if you can give more detailed sequence in timeframe settings with filter activities.
1) When you selected the data to be copied, the data range highlighted to be copied (when you selected the data) did not include the time range that you want. - verify if your selection of data to be copied includes the PF date
2) maybe a hardware limitations of your computer RAM - may need to increase
Hi shahul
When I did it i copied from the top of the wbs, I Aldo tríed with the select all comand, and even if the time scale is set from the project start to the project finish, some of the columns were not copied
Member for
8 years 9 monthsHi all, I also
Hi all,
I also encountered the same issue, but when I tried to select the “Hide if empty” check box under the “Group and Sort” tab all the date(month) which is empty will not be included when I paste it to excel sheet. It will only copy the PS and PF date of the project.
Member for
16 years 3 monthstry ctrl-C for copy then
try ctrl-C for copy then ctrl-v to paste as in any winidows based application
Member for
9 years 8 monthsI am facing a similar issue.
I am facing a similar issue. on the assigment view, I have done the grouping by Resource name and then WBS. I have checked "Show Grand Totals" in Display options. After I selecting this view (Ctrl+A) when I try to copy (Ctrl+C), the Total, Resource name and WBS are getting de-selected and I cannot copy/paste that to excel sheet. I tried this with changing the grouping to Resource ID name, still facing same issue. What is the cause of this issue and what is the solution?
Member for
16 years 3 monthsSelect the first month and
Select the first month and data press the shift and control key (HOLD THEM BOTH DOWN) now go to the right and select the last month of your data
Member for
12 years 9 monthsHi all,I had the same problem
Hi all,
I had the same problem occured to me as well. F5 Refresh command did not work for me.
However, changing the levels in Grouing to 'Resource ID Name (Levels ...)' solved the problem of copying and pasting directly from P6. Now I can use my Ctrl+C. Hope it helps.
Regards,
Talgat Baimukanov
Member for
12 years 9 monthsHi all,I had the same problem
Hi all,
I had the same problem occured to me as well. F5 Refresh command did not work for me.
However, changing the levels in Grouing to 'Resource ID Name (Levels ...)' solved the problem of copying and pasting directly from P6. Now I can use my Ctrl+C. Hope it helps.
Regards,
Talgat Baimukanov
Member for
16 years 3 monthsnot sure why but this
not sure why but this solution always works for me
work around is to use the snipping tool and take a screen shot of the area paste it into excel and manually duplicate the screen shot.
Member for
10 years 1 monthHi Zoltan, Thank you for your
Hi Zoltan,
Thank you for your reply.
I already made that what you had explained but still the same I cannot extract the exact data I wanted to get.I am using now report wizard which will take time.I was still hoping that you can provide more another options.
Hello Robin,
Pressing F5 or refreshin the program still didn't work out.Doing report wizard was my last option as of now that is taking time.Hope you can provide more options.
Thanks
Member for
15 years 2 monthsHi all,This is a very common
Hi all,
This is a very common issue, and has to do primarily with hardware constraints. If you are copying from the resource assignments table to excel for s-curves etc, sometimes it does not allow you to select the entire range.
Quite simple, hit F5 to refresh data, this should most of the time work, and then you can re-select all the data, alternatively restart your P6.
Member for
16 years 3 monthsI do not know what you mean
I do not know what you mean by setting the time scale. All you do is highlight the values you want from when want to start to copy them to when you want to finish copying them.
Select the first month and data press the shift and control key now go to the right and select the last month of your data
leave go of the shift key and the control key and press control-v
in excel press control-v
done
Member for
10 years 1 monthI already set the timeframe
I already set the timeframe to Baseline Project start and finsih manually by costumizing but still the same output I got.
Thanks for your reply.
Member for
16 years 3 monthstry going a few months PAST
try going a few months PAST (to the right of) the PF date when highlighting then copy then paste
Member for
10 years 1 monthI face the same problem with
I face the same problem with this one and it will be much more help if you can give more detailed sequence in timeframe settings with filter activities.
Thanks,
Member for
10 years 1 monthI face the same problem with
I face the same problem with this one and it will be much more help if you can give more detailed sequence in timeframe settings with filter activities.
Thanks,
Member for
13 years 9 monthsI think that probably1) When
I think that probably
1) When you selected the data to be copied, the data range highlighted to be copied (when you selected the data) did not include the time range that you want. - verify if your selection of data to be copied includes the PF date
2) maybe a hardware limitations of your computer RAM - may need to increase
Member for
13 years 5 monthsBy Selecting all from Edit
By Selecting all from Edit and then Copy-You can pull in dates...todays and furture
I cannot find to pull past history-progressed history.
Also, it will only copy over a total assigned per day-I can not get it to copy over 2-shifts-even though I have it displayed??
odd...I'm in P7 learning something new every day and scratching my head daily as well lol.
Member for
13 years 5 monthsBy Selecting all from Edit
By Selecting all from Edit and then Copy-You can pull in dates...todays and furture
I cannot find to pull past history-progressed history.
Also, it will only copy over a total assigned per day-I can not get it to copy over 2-shifts-even though I have it displayed??
odd...I'm in P7 learning something new every day and scratching my head daily as well lol.
Member for
21 years 1 monthWe use a P6 report to do
We use a P6 report to do this, not a screen copy.
Member for
16 years 11 monthsHi Maria del Mar Naz Last
Hi Maria del Mar Naz
Last Option is to check one by one and copy in excel or check by installing in another system
Regards
Shahul
Member for
14 years 2 monthsI am using p6.7 any idea of
I am using p6.7 any idea of what the reason may be?
Member for
16 years 11 monthsHi Maria del Mar Naz I do
Hi Maria del Mar Naz
I do agree,because it happened to me while using P6.1 try using P6.7 it works well
Regards
Shahul
Member for
14 years 2 monthsHi shahul When I did it i
Hi shahul
When I did it i copied from the top of the wbs, I Aldo tríed with the select all comand, and even if the time scale is set from the project start to the project finish, some of the columns were not copied
Member for
16 years 11 monthsHi Maria del Mar Naz Click
Hi Maria del Mar Naz
Click and copy form the top WBS and paste in excel it works based on time scale settings
Cheers
Shahul