Calenders may seem the same in P3 and P5. But P3 has day or hour, depending on your parameter setting. P5 always has hours per day. This can be different to the parameters under

Admin --> Admin Preferences --> Time Units.

Hours per day maybe is not the same --> Put ot to the same rate, e.g. 8 hours per day.

If you Plan with days in P3, days are stored, whereas P5 always stores hours.

Hope, this will help.