No offence taken. Ive been using this software for a few years now and always find something else to learn and theres sometimes half a dozen ways to do it.
There is no option to do this. Although it should be possible to define a new set of bars to reflect original baseline and report progress against these. It should be ...
Member for
22 years 3 months
Member for22 years4 months
Submitted by Kevin Button on Thu, 2007-01-18 17:32
Not sure that I fully understand what you need but you might need to play with some new bars and create one that uses the Plan Bar for the timescale and have the % Complete displayed on this bar.
Member for
22 years 8 monthsRE: Current progress against baseline?
Not sure this is what you ask for but you can use
"View"
"Progress Spotlight"
This will give you a progress line for with the data date line show whether the activity is ahead of behine schedule
HTH
Alex
Member for
24 years 5 monthsRE: Current progress against baseline?
I am struggling with same problem.
I can display bars for baseline OK
When I apply progress bars, progress is shown from actual start not baseline start?
In P3 %progress was shown from Target start date?
Member for
22 years 3 monthsRE: Current progress against baseline?
No offence taken. Ive been using this software for a few years now and always find something else to learn and theres sometimes half a dozen ways to do it.
Cheers
Member for
20 years 10 monthsRE: Current progress against baseline?
Kevin, funny, now I read it again, your right, sorry no offence intended.
I just havent seen baseline progress done yet in P3e.
Member for
22 years 3 monthsRE: Current progress against baseline?
...define a new set of bars to reflect original baseline and report progress against these...
Which is what I was suggesting anyway, just said it a different way.
Member for
20 years 10 monthsRE: Current progress against baseline?
There is no option to do this. Although it should be possible to define a new set of bars to reflect original baseline and report progress against these. It should be ...
Member for
22 years 3 monthsRE: Current progress against baseline?
Not sure that I fully understand what you need but you might need to play with some new bars and create one that uses the Plan Bar for the timescale and have the % Complete displayed on this bar.