Thanks a lot Alex, I’ll give it a go.



Cheers,



Matthew Lovkis

Member for

22 years 8 months

Matthew



Is your activity type is Fix Unit/Time, if that is the case then you cannot change the Unit/time for the activity.



What I suggest is to change you activity type to fix duration (Be careful to check with your acitivity duration) change the resource UPT, change back the activity type to fix UPT.



This should do the job



HTH