Using Multiple Rate Types

Member for

19 years 10 months

Thanks Nigel, unfortunately most of our clients (e.g Network Rail) will want and expect to recalculate forecast activity costs based on staff resource rates. Hence the need to include markup in the rate.



Paul

Member for

19 years 6 months

Paul

Done the same as David. As he says it works. Another way I have used to a base rate plus an expenxes addition. Depends upon how you need to show the costs. In that example I need to show an overall cost only including expenses. Not as elegant.

Cheers

Nige

Member for

19 years 10 months

Thanks David, I’ve used a similar work around myself using a global change to modify the resource ID to the one with the rate I need. I’m hoping that I’m missing something e.g that under admin you can increase the number of rate types.



Paul

Member for

21 years

Paul,



Hard. The only work around I have used is to start the hierarchical resource dictionery with the rate. E.G. the resource code is 45-Engineer, 48-Engineer. Not elegent. It works.