yes I am saying you an produce predicted cash flw/eard value for the project at any level if that is what is required. This can be summaized up to a comany or enterprise level at differnet phases.



I am not sure that this is wha you require.


Member for

22 years 5 months

Hi,



if you are trying to produce a projected cash flow you use the budget feature, or make a resource named proejct cash non material, and then level of balance actvity type. You can then use the resoure curves to spread the money over the time period.



Regards



Tim Readman