Primavera Project Planner - P3 Member for 18 years 7 months Member for 18 years 8 months Submitted by Rommel Ramirez on Fri, 2007-03-16 05:59 Permalink RE: Splitting activities in P3 Guys, Using the date has no effect on the splitting but adding its duration instead, Please try to create a separate calendar for that certain activity and make non-working date as you plan and then assign it afterwards. Hope itll help. Rgrds, Mel Member for 20 years 5 months Member for 20 years 5 months Submitted by Jose Frade on Fri, 2007-01-05 07:42 Permalink RE: Splitting activities in P3 Hello. Go to Date form when in that activity and register a stop and restart dates. Hope it helps. BR JMFrade Log in or register to post comments
Member for 18 years 7 months Member for 18 years 8 months Submitted by Rommel Ramirez on Fri, 2007-03-16 05:59 Permalink RE: Splitting activities in P3 Guys, Using the date has no effect on the splitting but adding its duration instead, Please try to create a separate calendar for that certain activity and make non-working date as you plan and then assign it afterwards. Hope itll help. Rgrds, Mel
Member for 20 years 5 months Member for 20 years 5 months Submitted by Jose Frade on Fri, 2007-01-05 07:42 Permalink RE: Splitting activities in P3 Hello. Go to Date form when in that activity and register a stop and restart dates. Hope it helps. BR JMFrade
Member for
18 years 7 monthsRE: Splitting activities in P3
Guys,
Using the date has no effect on the splitting but adding its duration instead, Please try to create a separate calendar for that certain activity and make non-working date as you plan and then assign it afterwards.
Hope itll help.
Rgrds,
Mel
Member for
20 years 5 monthsRE: Splitting activities in P3
Hello.
Go to Date form when in that activity and register a stop and restart dates.
Hope it helps.
BR
JMFrade