I would suggest you copy the project, delete the activities, then copy the activities from the old project and paste into the new and select the increment you require when pasting.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
Member for
22 years 4 monthsRE: ACT ID INCREMENT
Pare,
[English only, please. The Moderator.]
Note: Back up your project first!
1. Select all activities and COPY.
2. Delete all Activities.
3. Paste using Auto Increment.
- set the starting number.
- set the increment.
Best,
Jorge
Member for
24 years 7 monthsRE: ACT ID INCREMENT
I would suggest you copy the project, delete the activities, then copy the activities from the old project and paste into the new and select the increment you require when pasting.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting