ACT ID INCREMENT

Member for

22 years 4 months

Pare,



[English only, please. The Moderator.]



Note: Back up your project first!



1. Select all activities and COPY.

2. Delete all Activities.

3. Paste using Auto Increment.

- set the starting number.

- set the increment.







Best,



Jorge

Member for

24 years 7 months

I would suggest you copy the project, delete the activities, then copy the activities from the old project and paste into the new and select the increment you require when pasting.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au