Problems in importing Excel files

Member for

16 years 3 months

of course it worked

Member for

15 years 11 months

Thanks Zoltan , it worked.

Regards

Member for

16 years 3 months

go to Projects DIRECTORY and make sure that your project is open

then click on teh Resources tab at the bottom then look on the lower left where it says Resource Assignment

UNCHECK Resources can be assigned to the same activity more than once.