PRMDB-1701-A importing fault code

Member for

16 years 3 months

he needs to get the previledges 

Member for

14 years

were importing xlm via the web interface.

the above imformation was very useful especially column x.

he has noticed a variation but does not have the privaleges to change it at the moment.

Kind regards Craig

i would like some more attention on this as i can't start without having this fixed.

Member for

14 years

ok were going through the primavera enterprise.

i have been told we can not do regular imports /experts.

Is this true.

we have togo through the web interface .

The web interface only works to a status report after importing that says failed.

kind regards Craig 

 

fairly urgent now

Member for

16 years 3 months

1. the excel file needs to be an xlsx

2.  job_data_x column in the dbo.JOBSVC table not displaying varbinary(max), null as a datatype.the solution is to run the sspm_settings.sql located in the database\scripts\<PM_$Version>\install directory.

To alter the job_data_x column type, run the sspm_settings.sql script against the database as the sa user.

This script can be found within in the P6 EPPM media files at database/scripts/install/PM_<$Version>/sspm_settings.sql



After the script is run successfully, confirm the dbo.JOBSVC column shows as job_data_x (varbinary(max), null)