Right-click export to Excel -> other layout doesn't give any activities

Member for

16 years 3 months

highlight them first then rigth click export to excel  

Member for

20 years 6 months

Why are you right clicking? In your activity view, press CTRL+A to select all, then CTRL+C to copy to clipboard, then Past einto an Excel worksheet.

Member for

6 years 8 months

I have DD+3D filter OR status 'in Progress'

It works to get the right view in P6, but when I export to Excel it doesn't give any results.

Member for

6 years 8 months

Wait...

 

It doesn't have to do with the righ-click methode.. It doesn't export at all.

It is a 3 day lookahead filter, so I think it has someting to do with the date.