Resource loading challenge

Member for

15 years 11 months

Johanness presentation below is the right procedure. This can be applied too using Quantities of Workloads.

Member for

15 years 9 months

Hi Martin

I have modeled the challenge in Primavera P6.

Resource optimization is finding the balance between the resource requirements and the resource availability.

The resource requirements you detail in the activity

The resource availability you detail in the enterprise> resources

In this case, I have 10 times 8 hours/day=80 hours/day requirement

I have detailed 9 times 8 hours/day=72 hours/day availability.

I leveled the resources and the result you see below.

Thrust this is clear 

Regards

Johannes

Simple, Free Image and File Hosting at MediaFire

Member for

22 years 4 months

Rafael - thanks, that's a useful suggestion.  I'll give it a go.  Obviously the numbers are higher, but the logic behind what you are suggesting should still work, if I create a resource with a limit of 5000 (being silly), assign 1 to each activity that can happen whenever, and 5000 to the one that can only happen on it's own.

Member for

21 years 8 months

  • Create a marker resource say Resource A with availability of 9 ea.
  • Assign 1 ea to the 9 activities that can happen at the same time.  If you want to set some prioritization do it.  A good resource leveling engine will respect the prioritization as long as it can yield shorter schedule duration.
  • Assign 9 ea to the activity that cannot happen while the other 9 activities.
  • Resource level. Check resource leveling by moving some activities to see if the requirement for Activity X holds after leveling.

If using effort hours translate availability and assignments to how your software works.

Challenge2018.08.22