Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2017-12-08 13:47 Permalink because you can use either because you can use either physical % complete, duration % complete or unit % complete to track your % complete you can not roll up certain % completes. This is like mixing apples, oranges and bananas. Try using actviity % complete Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2017-12-08 13:47 Permalink because you can use either because you can use either physical % complete, duration % complete or unit % complete to track your % complete you can not roll up certain % completes. This is like mixing apples, oranges and bananas. Try using actviity % complete
Member for
16 years 3 monthsbecause you can use either
because you can use either physical % complete, duration % complete or unit % complete to track your % complete you can not roll up certain % completes. This is like mixing apples, oranges and bananas. Try using actviity % complete