create an activity for that particular wbs and give it the activity TYPE of wbs summary then it will roll up and summarize that particular wbs for you. You can not roll up the wbs in the way that you are doing it becasue activities can use different wats to mecasure their progress you can use duration % complete, physical % complete or units % complete. So if you tried to summarize them by youe would be mixing applles and oranges and bananas. The soultion is to use WBS summary.
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
9 years 3 monthsThank you Mr. Zoltan. If
Thank you Mr. Zoltan.
If resource unit per price is not zero then % progress will roll up with every status update. I have done it.
Member for
16 years 3 monthscreate an activity for that
create an activity for that particular wbs and give it the activity TYPE of wbs summary then it will roll up and summarize that particular wbs for you. You can not roll up the wbs in the way that you are doing it becasue activities can use different wats to mecasure their progress you can use duration % complete, physical % complete or units % complete. So if you tried to summarize them by youe would be mixing applles and oranges and bananas. The soultion is to use WBS summary.