Store Period Performance

Member for

16 years 3 months

is you started now would get one big dump of cost during this update

you can manually fix this

the work around is to use it from day 1

this is how to edit store period performance

To edit stored actual units or cost for a past period
 
If you have already defined the financial period,
Select Edit User preference
Then select Application - at the bottom under column level- select the
financial period for which you want to edit the past period performance of
any specific resource assignment-then close
Next go to the Activity mode
Click the resource tab
Right click on resource detail & customize-add columns from "Financial
Period Value"- Press ok-
Now in the Details window you can edit the past performance actual there.