if you can get your activities lined up or group another way then you can add a column for the wbs and then do the 1st one and then do a fill down
option #2
you can export the activites to excel when you export them if they have not been assigned they wil automatically take the wbs of the project id that is the highest level. You can then change them in excel and import them back into p6
Member for
14 years 7 months
Member for14 years7 months
Submitted by Zahid Rehman on Thu, 2017-09-21 09:04
Member for
16 years 3 months2 optionsoption #1if you can
2 options
option #1
if you can get your activities lined up or group another way then you can add a column for the wbs and then do the 1st one and then do a fill down
option #2
you can export the activites to excel when you export them if they have not been assigned they wil automatically take the wbs of the project id that is the highest level. You can then change them in excel and import them back into p6
Member for
14 years 7 monthsI was looking for the
I was looking for the solution of the same issue since last one week but in vain.... Thanks Chandran , this tip really worked...
Member for
16 years 3 monthsadd a column for wbs do the
add a column for wbs do the first one then do a fill down
Member for
13 years 10 monthsSelect the activities
Select the activities (Ctrl+Activity).
Move the cursor to the left side of the activity table. Cursor with small rectangle appears.
Now drag the activities to the needed WBS.