Problems when i try to update the advance of one task

Member for

22 years 9 months

Hello,

A few questions for you to answer before I am able to help you:

* which MSP release are you working with?

* in which field are you entering the data? %progress (duration), %work progress (work), %physical progress?

* how have you setup the project calculation option?

Thanks