Updating / rescheduling project - MSP 2013

Member for

16 years 6 months

Hi Andrew

Many thanks for your reply.  After about an hour of searching on the net yesterday, I got the same answer and it is exactly what I needed. 

I have no idea about how the previous versions worked because I am mostly used to Asta Powerproject, even though I've used MSP a fair bit (say 75/25 in favour of Asta).  When I used MSP it was purely progressing other peoples programmes so it was pretty much set up how it was needed.

This new job has got me on the newest version and I'm doing all my own programmes and needed to give something to the guys on site ASAP, so I've been thrown in the deep end with it.  Which, for me, has been a great way to learn a new bit of software!

 

Again, thanks for your reply :o)

Member for

21 years 7 months

If it's the same as MSP 2010, there are two sequences of actions to do

Firstly:-

  1. File
  2. Options
  3. Schedule
  4. Tick "Split in progress tasks" [or press alt p]

Secondly

  1. Highlight the specific task
  2. Go to Task on the Ribbon
  3. Move
  4. Incomplete parts to status dates.