time scale of project 2007

Member for

17 years 9 months

Liu,

You can do it like this:

  1. In Gantt Chart Timescale chose Day / Week/ Month from Start
  2. Create and show customer field, which will calculate the task start date and task finish date from the Project Start

    e.g.

    Task Start from Project Start (Calendar Days)(Number1)=DateDiff("d";[Project Start];[Start])+1

This is how your schedule will look like then