Filters in MS Project

Member for

22 years 9 months

Hello,

such filter already exists in MS Project, all versions: go to Project, Filter for, More filters

then select "Should start / finish before"

Alexandre

Note: as I am working with MSP in French, the filter name might be slightly different.