Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2010-04-11 13:00 Permalink RE: Different weighting to activities LO Gary, no, it is not possible to have different weighting for different activities in MS Project; or, you should use custom fields and formulas for that. Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2010-04-11 13:00 Permalink RE: Different weighting to activities LO Gary, no, it is not possible to have different weighting for different activities in MS Project; or, you should use custom fields and formulas for that. Alexandre
Member for
22 years 9 monthsRE: Different weighting to activities
LO Gary,
no, it is not possible to have different weighting for different activities in MS Project;
or, you should use custom fields and formulas for that.