Microsoft Project Member for 19 years 5 months Member for 19 years 5 months Submitted by James Griffiths on Mon, 2006-08-21 14:52 Permalink RE: BCWS at Task Level not calculating Colleen, Have set the status-date, via Project>Project Information? James. Member for 21 years 8 months Member for 21 years 8 months Submitted by Tom Hadley on Sat, 2006-08-19 21:59 Permalink RE: BCWS at Task Level not calculating Work around Buy a program that works properly, get yourself trained in Earned Value not just how to use MSProject Distrust absolutely any cost calculations done by MSProject I will train you just email me PMwork1@bigpond.net.au Regards tom Log in or register to post comments
Member for 19 years 5 months Member for 19 years 5 months Submitted by James Griffiths on Mon, 2006-08-21 14:52 Permalink RE: BCWS at Task Level not calculating Colleen, Have set the status-date, via Project>Project Information? James.
Member for 21 years 8 months Member for 21 years 8 months Submitted by Tom Hadley on Sat, 2006-08-19 21:59 Permalink RE: BCWS at Task Level not calculating Work around Buy a program that works properly, get yourself trained in Earned Value not just how to use MSProject Distrust absolutely any cost calculations done by MSProject I will train you just email me PMwork1@bigpond.net.au Regards tom
Member for
19 years 5 monthsRE: BCWS at Task Level not calculating
Colleen,
Have set the status-date, via Project>Project Information?
James.
Member for
21 years 8 monthsRE: BCWS at Task Level not calculating
Work around
Buy a program that works properly, get yourself trained in Earned Value not just how to use MSProject
Distrust absolutely any cost calculations done by MSProject
I will train you just email me PMwork1@bigpond.net.au
Regards
tom