Showing Planned % in MSP

Member for

21 years 3 months

Maria,

You can try to calculate with the customize field from tool and put the formula in the number field(custom date - early start date)*100/(early finish-early start), that will show the planned progress and you already have the actual progress field.

Where the custom date you can say "date1" and put the date in the date1 field from which date you want to calculate % planned progress.

Hope this will work.

Member for

24 years 7 months

Does all the activities in the schedule need to be linked for ’update progress’ function to work. No.



-Does ’update progress’ function works fine for activities with constraints too? Yes.



Just put together a small schedule and test the function before using it on a live project.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

Member for

22 years 8 months



Thanks for the prompt reply Paul.



Couple of quick questions:



-Does all the activities in the schedule need to be linked for ’update progress’ function to work.



-Does ’update progress’ function works fine for activities with contraints too ?

Member for

24 years 7 months

There are many ways this can be achieved but I feel the simplest way I can see to achieve the result you require is to:

1. Take an unprogressed copy of the schedule,

2. Use Tools, Tracking, Update project and update the project to the current status date. MSP will calculate both the detailed and summary % complete based on the work progressing according to plan.

3. Copy and past the values from the % Complete Column into a number or text column of your current schedule.



You will need to add or remove lines in your unprogressed schedule to match your current schedule.



The summary durations are calculated on the sum of actual durations divided by the sum of all the durations and does not give an accurate measure of progress unless all tasks are of equal value.



Hopfully some one else may have a simpler solution for you.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

Member for

22 years 8 months

Dear paul,



I have answered your questions in BOLD:



1. What version of MSP are you using - MSP - 2000



2. Is the schedule resourced - NO ITS JUST A SIMPLE BAR CHART



3. Have the resources rates and does the schedule include all the costs - NO



4. Do you want the % Planned based on time, units or costs? - KNOWING PLANNED % BASED ON TIME WOULD BE OK



Would appreciate a detailed reply.


Member for

24 years 7 months

Mary JoAnn



I do not think there is a specific field for this data but it may be possible to calculate this information in a Custom field.



You need to supply a more information before this question may be answered.



1. What version of MSP are you using

2. Is the schedule resourced

3. Have the resources rates and does the schedule include all the costs

4. Do you want the % Planned based on time, units or costs?



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au