Resource Dependant

Member for

16 years 3 months

no hence the name RESOURCE DEPENDENT. If you want to do this change the activity type to task dependent.

if an activity has been assigned as a resource dependent type of task then the duration will be based on availability for that resource to work on that activity and it will use the RESOURCES CALENDAR NOT the activity calendar.

Try to make the resource calendar as same as the activity calendar and it might do what you want.