Material Resource - Applying an additional fixed cost

Member for

16 years 3 months

filer for what you want to change

go to tools

global change 

on the right select New

up top under Slect Subject area change that to Activity Resource Assignments

where resource id name equals whatever the resource name is

then budgted costs = budgted costs * .06

 

On the right select change 

then on the bottom select commit Chnagest

Member for

16 years 3 months

Is any way to material resource as primary resource - thats depends on if the # Units of the material is driving the activity

Second how to assign of unit of measure such as hour for labor and non--labor - yes go to the resource and look under the  

details tab and there is a drop down there for unit of measure. If you do not see the one you want you can add it by going to Admin then Admin Categories then Units of measure 

Third in resource tab of activity details of update primary resource is any setting to automatically update other resource

go to Projects and on the Resources tab under Resource Assignments set the settings there

Member for

18 years 8 months

Is any way to material resource as primary resource

Second how to assign of unit of measure such as hour for labor and non--labor

Third in resource tab of activity details of update primary resource is any setting to automatically update other resource