Oracle Primavera - PM6 Member for 16 years 10 months Member for 16 years 10 months Submitted by Kevin Rayner on Mon, 2019-03-25 17:42 Permalink You are aware that when You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline? Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-03-22 13:04 Permalink how come you are mixing how come you are mixing planned start date with finish dates ? actual start = planned start actual finish = planned finish Log in or register to post comments
Member for 16 years 10 months Member for 16 years 10 months Submitted by Kevin Rayner on Mon, 2019-03-25 17:42 Permalink You are aware that when You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-03-22 13:04 Permalink how come you are mixing how come you are mixing planned start date with finish dates ? actual start = planned start actual finish = planned finish
Member for
16 years 10 monthsYou are aware that when
You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?
Member for
16 years 3 monthshow come you are mixing
how come you are mixing planned start date with finish dates ?
actual start = planned start
actual finish = planned finish