Global change not working for baseline programme

Member for

16 years 10 months

You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?

Member for

16 years 3 months

how come you are mixing planned start date with finish dates  ?

actual start = planned start

actual finish = planned finish