Change Duration when adding extra Resource

Member for

13 years 4 months

How do I close this post?

 

Admin,, please mark this post as Solved.

Member for

13 years 4 months

YES! the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...

 

that was the setting I couldn't remember, thanks Alexandre.

Member for

22 years 9 months

Hello guys,

do not forget to change the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...

this way, P6 will split the 100 hours assigned to Resource #1 between the original and the additional resources

Alexandre

Member for

16 years 3 months

you can change the duration TYPE to fixed units. As you change the units this will change the duration. 

you can also change the activity type to resource dependent. This will use the resource calendar as opposed to the activity calendar. You usually use this if you have multiple resouces on the same activity.