you can change the duration TYPE to fixed units. As you change the units this will change the duration.
you can also change the activity type to resource dependent. This will use the resource calendar as opposed to the activity calendar. You usually use this if you have multiple resouces on the same activity.
Member for
13 years 4 monthsHow do I close this
How do I close this post?
Admin,, please mark this post as Solved.
Member for
13 years 4 monthsYES! the User Preferences,
YES! the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...
that was the setting I couldn't remember, thanks Alexandre.
Member for
22 years 9 monthsHello guys,do not forget to
Hello guys,
do not forget to change the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...
this way, P6 will split the 100 hours assigned to Resource #1 between the original and the additional resources
Alexandre
Member for
16 years 3 monthsyou can change the duration
you can change the duration TYPE to fixed units. As you change the units this will change the duration.
you can also change the activity type to resource dependent. This will use the resource calendar as opposed to the activity calendar. You usually use this if you have multiple resouces on the same activity.