Cash Flow report without resource loading in P6

Member for

21 years 8 months

The above example is very simple for illustration purposes but it is not unusual to have different budgets, perhaps one for purposes of Billings, and another for purpose of cost control where you will track labor, equipment, materials, subcontracts and other cost types for each cost account. In such case you level only cost accounts that define your financial constraints.  The use of Cost Centers make it easy to select the account groups of concern. 

Member for

16 years 3 months

thanks Tom good to know I never uses expenses 

Member for

18 years 11 months

Zoltan, yes you can.  Activity Usage Profile using Cost instead of Units incorporates all the Expense tab data. 

Member for

16 years 3 months

I am not sure that you can get an S curve using expenses

Member for

8 years 7 months

you can use Expenses to load cost on all activities you want,

add one expense on an activity then export on excel then add the cost and import it again on primavera.

Member for

18 years 11 months

I'd agree that cost loading is most commonly done through resource loading of a lump-sum resource as Zoltan has laid out.  The restriction, "...without resource loading in P6...." can be strictly satisfied by loading costs through the Expenses tab.  Although this is not the stated purpose of the Expenses tab, some contract specifications explicitly require it (not sure why.)  

Member for

16 years 3 months

add a resource call LUMPSUM or what ever

filter for all of the activities that you want to cost load

select edit select all

right click and select assign 

then select  resources

then select the new resource that you created

now in the resource tab under budgeted cost

assign the cost for each of teh actyivities

when done you can either select view show on bottom activity usage spreadsheet

or view show on bottom resource usage profile thsi will give you your cost curve

Member for

7 years 2 months

How can I prepare a report with dollars for each activity?

Member for

16 years 3 months

putting the budget against each activity is resource loading its loading with dollars not manhours