Weird Problem in P6

Member for

16 years 3 months

GLAD i COULD HELP

Member for

9 years 3 months

Thanks a lot Mr. Zoltan.

Member for

9 years 3 months

Thank you Mr. Steven.
Your reply was very convincing and clear.

Member for

8 years 1 month

adab,

If ALL activities are linked Finish to Start, then all activities should be on the Critical Path, as there is only 1 path.

The first activity of WBS 1 is linked to the Start Milestone, then all activities linked Finish to Start under this WBS. 

If the Last Activity of WBS 1 is linked to the First Activity of WBS 2 & this sequence is repeated through all the WBS Levels, with the last activity of WBS 7 being linked to the Finish Milestone, then there is 1 path so all activities will be critical.

If the WBS Activities are linked as shown in Jithin's post & the total duration of each path is the same then all will be critical, as you may have 7 different paths from the Start Milestone to the Finish Milestone - The Float for each path would be the same & all activities would be driving the critical path.

If 1 activity took longer during execution, then this path would become the critical path.

If you increase the duration of 1 activity, do all activities remain critical, or is a new critical path identified?

Do you have any constraints applied on your Project?

Steven

Member for

9 years 3 months

Hello Steven.
Yes there is relationship between WBS of finish to Start.

Member for

8 years 1 month

adab,

Am I misreading your last post:

"Is it possible that even in a small project of primavera having 5 or 6 activities all in Finish to Start relationship, All activity will become red in ghant chart?"

If ALL activites are linked Finish to Start in a small project, then ALL would be Critical & Red in the Gantt Chart.

Are there any relationships between the different WBS? 

Steven

Member for

16 years 3 months

if you have a constraint date or a project must finish by date that will dtermine the criticaally of it.

if EVERYTHING is FS then depending on the duration it wil dtemeine the critical path 

Member for

14 years 7 months

Hi Adab,

May be all the Activity under Different WBS on FS relationship has equal dutation and is pushing the Finish Milestone then all the activity would be Critical. Check that too. 

WBSActivityDurationTotal DurationFloat to Finish MilestoneWBS 1Activity 12  140WBS 1Activity 2 4 WBS 1Activity 3  8WBS 2Activity 15  140WBS 2Activity 2 6 WBS 2Activity 3  3

In this all the Acivity would be Critical if under FS relationship.

Regards

Jithin

Member for

9 years 3 months

Thank you Jithin.
I have tried all this but sadly its not working.
Is it possible that even in a small project of primavera having 5 or 6 activities all in Finish to Start relationship, All activity will become red in ghant chart?
Checked bar option too, everything alright there.
Schedule option is set to longest path method. Still its happening.

Member for

14 years 7 months

Hi Adab,

Look at the Project - Must Finsih Date and then go to Settings of the Project and check what has been selected for "Define Critical Activities.

If you have selected " Longest Path" then the longest path in your schedule would be Critical. 

If you have selected "Total Float less than or equal to" - No days - All the activity which has a total float less or equal to that duration would be critical.

Regards

Jithin