if an activity has and actual start then the start date gets the A letter next to the date the same holds true for an activit yhaveing an actual finish date
So run these 2 global changes
Global change #1 for completed activities
Where activity status equals completed
then planned start = Start
and planned finish =Finish
Global change #2 for activities started but yet finished
Member for
16 years 3 monthsyes here is the
yes here is the secification
Where Activity status = completed
Then
Planned Start = Start
Planned Finish = Finish
****************
Where Activity status = completed
Then
Planned Start = Start
Planned Finish = Finish
Member for
19 years 4 monthsNot sure if you meant "actual
Not sure if you meant "actual start" instead of "start" - Nonetheless, I carried a global change using both criteria but no luck
****************
Where Activity status = completed
Then
Planned Start = Actual Start
Planned Finish = Actual Finish
****************
Where Activity status = completed
Then
Planned Start = Start
Planned Finish = Finish
Despite running above crieteria I have couple activities, where Planned Start and finish does not match Actual Start and Finish resp.
Any help in this regard is appreciated
Member for
16 years 3 monthsif an activity has and actual
if an activity has and actual start then the start date gets the A letter next to the date the same holds true for an activit yhaveing an actual finish date
So run these 2 global changes
Global change #1 for completed activities
Where activity status equals completed
then planned start = Start
and planned finish =Finish
Global change #2 for activities started but yet finished
Where activity status equals in progress
then planned start = Start