yes here is the secification 

Where Activity status = completed

Then

Planned Start = Start

Planned Finish = Finish

****************

Where Activity status = completed

Then

Planned Start = Start

Planned Finish = Finish

Member for

19 years 4 months

Not sure if you meant "actual start" instead of "start" - Nonetheless, I carried a global change using both criteria but no luck

****************

Where Activity status = completed

Then

Planned Start = Actual Start

Planned Finish = Actual Finish

****************

Where Activity status = completed

Then

Planned Start = Start

Planned Finish = Finish

Despite running above crieteria I have couple activities, where Planned Start and finish does not match Actual Start and Finish resp.

Any help  in this regard is appreciated

Member for

16 years 3 months

if an activity has and actual start then the start date gets the A letter next to the date the same holds true for an activit yhaveing an actual finish date

So run these 2 global changes

Global change #1 for completed activities 

Where activity status equals completed 

then planned start = Start

and planned finish =Finish

 

Global change #2 for activities started but yet finished 

Where activity status equals in progress 

then planned start = Start