I think it is a question of the same basic questions coming up time after time. People should take the time to check previous threads sometimes, as the questions have been answered in depth before. When things are a bit slack, I normally browse through some of the older threads.
I do not have a problem with helping out, and will always answer a question if I have an answer.
Regards,
Philip
Member for
20 years 7 months
Member for20 years7 months
Submitted by Anand Kulkarni on Fri, 2005-05-27 02:48
As a planner he/she must have a good knowledge on productivity rates for all the trades. This only can be achievable if the planner spend his time and observe how any particular works are carried on at site. Also the planner must know how many teams/workers required to complete the job and what is the timeframe. To master this the planner at least need to complete 1 or 2 projects from start to finish.
As for software, believe the planner can gain the knowledge after attending few courses, fully operate and utilise it in a project.
So to become a good planner, site experience always overrule the software experience.
Regards.
Member for
21 years
Member for21 years
Submitted by Philip Jonker on Thu, 2005-05-26 10:53
As for us oldy planners, I have been writing programs in Access, for at least 8 years, and have a good knowledge of most planning software. Don’t believe computors is the domain of the young ones. I was programming engineering applications in 1972.
When I mentioned dinosaurs in an earlier posting, it is the fact that we stick to methods that work, and will work for a long time still.
Regards
Philip
Member for
20 years 6 months
Member for20 years6 months
Submitted by Puneet Gupta on Thu, 2005-05-26 10:42
Im from Welcom Software. Open Plan has indeed matured. Ive used P3 and P3e(having worked directly for the company for many years).
In my humble opinion, one of the things I like about Open Plan is that it has a lot of the functionality we know and love about P3 and more, and does not have what I call the "extra fluff" found in P3e.
We know P3 users are important and developed interfaces that allow bi-directional import/export of P3 data.
Again i would like to say both have some good as well as bad features, i am also a certified instructor for Primavera products, and currently working with a petrochemical company. As a trainer in P3V3 training i loved to say P3 E/C is much much better & in P3 e/c training my statement was P3V3 is better...so all marketing strategy....Also Primavera Marketing strategy is to sell Primavera E/c to clients, so that they can force their consultants/Contractors to use the same.
Remember that PRIMAVERA is a Global leader in scheduling software.
Regards
Member for
21 years
Member for21 years
Submitted by Philip Jonker on Wed, 2005-05-25 11:12
Bill, I don’t think the words is narrowminded, but practical.
As for the stories of Primavera trying to stop P3w and replace it with P3e or whatever, I believe that it is time for Primavera to come clean, and make a statement as to what their policy is. I believe there is always room for improvement, and there is certainly a few, that could help in P3w.
However, on the other side of the coin there is other software companies like Welcome, who I believe have stabilised their software. So we are not bound to follow Primavera blindly. I believe the greater part of marketing is finding out what your consumers want. This does not seem to be the case in the Primavera book.
I greatly appreciate your feedback and share your opinion regarding P3Win. Both the owners rep and the local Primavera rep have strongly encouraged me to transition from P3Win to P3 e/c. However, after polling all users I know who have 20+ years scheduling experience, all say the same thing - stick with P3Win. Two of the users polled had taken the 3 day course for P3e/c and those two were the two strongest opponents against P3e/c. Even the Primavera rep keeps telling me that p3Win is being phased out and I am going to have no choice but to switch to P3e/c. If that truly is the case, then Primavera better make drastic improvements to P3e/c so those of us in construction who are avid P3Win users dont start a revolt.
Take care,
Scott
Member for
21 years
Member for21 years
Submitted by Philip Jonker on Wed, 2005-05-25 08:05
I agree with you completely, if the tool can do the job why re-invent the wheel. I think a big problem is so-called user friendliness, ie "cater for the folks who can’t think for themselves". I evalued P3e a couple of years ago, and in my opinion, P3 was still the better tool, even though the P3e price a that stage was almost $900-00 less than P3.
As a matter of interest, have you ever used Open Plan V4 (dos)? We were still using it on projects as late 1996, long after the advent of windows. I still believe it was the most flexible planning tools I have used. The trick was that you had to be able to use dbase, which is fairly simple. Even simpler now with the advent of excel and similar spreadsheet programs. The problem was that Welcom software went the same route as Primevera, and started a new product ie Open Plan Professional, which was totally rigid, and which could not do anything near as well as OP v4, and as a result OP virtually disappeared for a few years.
We probably sound like dinosaurs, but at the end of the day we understand our discipline, and do not need these new-fangled gimmicks to improve our planning. Who cares about 16 bit and 32 bit, if you get the right answers?
Regards
Philip
Member for
22 years 6 months
Member for22 years6 months
Submitted by Syed Ali Hasan on Wed, 2005-05-25 07:10
The reason for tossing out P3WIN if believe was due to its 16 bit architecture and as the technology improved, Primavera had to move to the 32 bit architecture or get Swallowed by other competitors.
Another reson was Portfolio management and not just project management which is the key to success as per recent trends.
I agree to you that we have very experienced users of P3WIN but I am sure they can easily learn or come to terms with P3 E&C in a matter of days. I infact give 2 days crash courses of P3e to experienced users of P3WIN to understand the new windows concepts and terminologies.
Best wishes,
Syed
Member for
22 years 6 months
Member for22 years6 months
Submitted by Syed Ali Hasan on Wed, 2005-05-25 06:41
By the way, it is not a book. It is a PDF document created by Primavera Systems, Inc for users who are planning to migrate data from P3 to P3e.
The book which you might be mentioning is also available from Primavera Systems, Inc has a user guide for Engg & Construction users.
I do not deny that P3 3.1 is a good solution but P3 E&C is also being developed and is better than what it used to be.
I am an certified instuctor for all Primavera Products from Primavera Systems, Inc and have provided implementation support to a different clients in different industries for the last 14 years.
Best regards,
Syed, PSP (From AACEI)
Member for
22 years 6 months
Member for22 years6 months
Submitted by Syed Ali Hasan on Wed, 2005-05-25 06:29
I have sent the same to couple of you through e-mail. It will be great to have your feedback as this will help the users of this thread to know the value and remove misconceptions of migrating from the classical P3 3.1 to Primavera Eng & Constrn or M&T or NPD or IT (Enterprise solution). Current version of the same is 4.1 and 5.0 (which will be released officially shortly) has really some more good features like resource planning and to top it all the UNDO function. I am working with 5.0 Beta version.
Best wishes,
Syed
Member for
20 years 8 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Wed, 2005-05-25 06:14
You have confirmed what others have told me. Would you mind expanding on your background and current experience with this subject so I may expand on our side of this debate. Thanks so much for your comments.
I have a similaar problem. I am using P3 and have 8 projects within 1 master schedule due to the many complex inter-relationships between them. An owners rep I have to report to is wanting me to separate my master schedule into 8 different project files so that when he downloads into P3e/c he can load one project at a time. My projects have codes that clearly identify them individually within my master project. So, what I did to solve the problem is set up a filter for each project within the master schedule and copied each project filter to a separate file. I then made backups of all 8 files for the projects for the owners rep so he can download each one as he needs to into p3e/c. My question is this, isnt there a simpler way that P3 e/c can read this information? Im just not a beliver in setting my master schedule up into the master project - sub-project format that the owner p3 e/c user says is required for him to properly download information.
Member for
20 years 6 months
Member for20 years6 months
Submitted by Puneet Gupta on Mon, 2005-05-09 01:42
I read that book ....but that book can not explain all these problems which comes only when you start working on it.
As my schedule is very simple, And when M/s primavera re-schedule the same schedule they find not slipping in dates, and when i re-schedule there comes .. a slppage in dates.
So its only problem setting....of P3 e/c
Regards
Member for
22 years 6 months
Member for22 years6 months
Submitted by Syed Ali Hasan on Sun, 2005-05-08 11:41
There is a P3 to P3e migration guide available from Primavera System, Inc. If anyone needs the same kindly send me a e-mail at syed.hasan@cmcs.ae and I would be glad to provide you the same. It is an excellent PDF document which explains all aspects which needs to be taken care of prior to migration of data from P3 to P3e.
Best wishes,
Syed Hasan
Member for
20 years 6 months
Member for20 years6 months
Submitted by Puneet Gupta on Sat, 2005-05-07 01:33
There are quite a few issues in P3ec where there are multiple possible settings where in P3 there is only one (built-in) setting.
The first that comes to mind is the calendar that relationship lags use. You must set the schedule in P3ec to use the ‘Predecessor’s Calendar’ if you want to be compatible with P3.
I assume that when you say that you have checked “everything” that you first compared the dozen or so CPM calculation settings. If not, then you haven’t begun to check for compatibility. Good luck!
Member for
20 years 6 months
Member for20 years6 months
Submitted by Puneet Gupta on Fri, 2005-05-06 02:18
if your resources are restricted then the leveled schedules may be different due to the difference in the scheduling heuristics even when the initial data are the same.
Vladimir
Member for
20 years 6 months
Member for20 years6 months
Submitted by Puneet Gupta on Fri, 2005-05-06 01:52
Can I rephrase the question, does anyone have (or know of) a list of the features in P3 and P3e/c that are not supported in the other product that are likely to cause a scheduling differences?
Whilst we can work through the differences as they crop up, a list of things to avoid by both parties will ensure that at least the exchanging of the data is angst free.
I have a list of differences between P3 and SureTrak that I use to set some upfront ground rules to ensure we do not use features that we are unable to replicate in the other product eg. The Interruptible scheduling option is not supported by SureTrak. SureTrak also only recognizes four of P3’s nine autocost rules.
A similar list for P3 and P3e/c would benefit all PPer’s who are in Puneet’s position.
Member for
22 years 10 months
Member for22 years10 months
Submitted by Ronald Winter on Thu, 2005-05-05 12:09
Interesting question. Instead of you looking at your schedule to determine what actually did cause the differences, you ask us to list all of the possible issues that you could be experiencing.
For one thing, P3ec does not support the Interruptible Activity setting of P3. If this setting is set to ‘Interruptible’ and you have activities that are constrained by relationships to both their starts and finish, then P3ec would display a difference.
Member for
22 years 7 months
Member for22 years8 months
Submitted by Dayanidhi Dhandapany on Thu, 2005-05-05 12:07
I think all the codes(resources,..etc)in P3 should match with the codes in P3e/c., also you have to check for Calendar for Scheduling Relationship Lag(both in P3 and P3 e/c should match like predecessor activity calendar or successor.....).
Member for
21 yearsRE: P3 TO P3 e/c Scheduling problem
Hi Bill,
I think it is a question of the same basic questions coming up time after time. People should take the time to check previous threads sometimes, as the questions have been answered in depth before. When things are a bit slack, I normally browse through some of the older threads.
I do not have a problem with helping out, and will always answer a question if I have an answer.
Regards,
Philip
Member for
20 years 7 monthsRE: P3 TO P3 e/c Scheduling problem
Are U trying to suggest that PP should have hierarchy of forum so that undue embracement is avoided?
Just on lighter vein!
Member for
20 years 8 monthsRE: P3 TO P3 e/c Scheduling problem
Hi guys,
Again it is PLANNING vs SOFTWARE.
As a planner he/she must have a good knowledge on productivity rates for all the trades. This only can be achievable if the planner spend his time and observe how any particular works are carried on at site. Also the planner must know how many teams/workers required to complete the job and what is the timeframe. To master this the planner at least need to complete 1 or 2 projects from start to finish.
As for software, believe the planner can gain the knowledge after attending few courses, fully operate and utilise it in a project.
So to become a good planner, site experience always overrule the software experience.
Regards.
Member for
21 yearsRE: P3 TO P3 e/c Scheduling problem
Hi Puneet,
As for us oldy planners, I have been writing programs in Access, for at least 8 years, and have a good knowledge of most planning software. Don’t believe computors is the domain of the young ones. I was programming engineering applications in 1972.
When I mentioned dinosaurs in an earlier posting, it is the fact that we stick to methods that work, and will work for a long time still.
Regards
Philip
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi
First of all i am from earth.
Secondly i do agree planner should have good logic which come only from site experiance.
But only site experiance is not sufficient, you should have a software expertise.
Most of the oldy Planners (experianced) lacks in it.
So now i can say if you want to be a good planner you should have good site experiance and expertise in software like MS-Access.
We in primavera thinks only in one direction ...critical path.
Try PERTMASTER, its a software based on PERT & Not on critical path.
Planning is something which requires logic and not only site experiance.
Member for
20 years 9 monthsRE: P3 TO P3 e/c Scheduling problem
Hi All,
Im from Welcom Software. Open Plan has indeed matured. Ive used P3 and P3e(having worked directly for the company for many years).
In my humble opinion, one of the things I like about Open Plan is that it has a lot of the functionality we know and love about P3 and more, and does not have what I call the "extra fluff" found in P3e.
We know P3 users are important and developed interfaces that allow bi-directional import/export of P3 data.
check it out www.welcom.com
Member for
21 yearsRE: P3 TO P3 e/c Scheduling problem
Hi Puneet,
Which planet are you from? :-)
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi all
Again i would like to say both have some good as well as bad features, i am also a certified instructor for Primavera products, and currently working with a petrochemical company. As a trainer in P3V3 training i loved to say P3 E/C is much much better & in P3 e/c training my statement was P3V3 is better...so all marketing strategy....Also Primavera Marketing strategy is to sell Primavera E/c to clients, so that they can force their consultants/Contractors to use the same.
Remember that PRIMAVERA is a Global leader in scheduling software.
Regards
Member for
21 yearsRE: P3 TO P3 e/c Scheduling problem
Hi Bill/Scott,
Bill, I don’t think the words is narrowminded, but practical.
As for the stories of Primavera trying to stop P3w and replace it with P3e or whatever, I believe that it is time for Primavera to come clean, and make a statement as to what their policy is. I believe there is always room for improvement, and there is certainly a few, that could help in P3w.
However, on the other side of the coin there is other software companies like Welcome, who I believe have stabilised their software. So we are not bound to follow Primavera blindly. I believe the greater part of marketing is finding out what your consumers want. This does not seem to be the case in the Primavera book.
Regards
Philip
Member for
20 years 8 monthsRE: P3 TO P3 e/c Scheduling problem
Bill,
I greatly appreciate your feedback and share your opinion regarding P3Win. Both the owners rep and the local Primavera rep have strongly encouraged me to transition from P3Win to P3 e/c. However, after polling all users I know who have 20+ years scheduling experience, all say the same thing - stick with P3Win. Two of the users polled had taken the 3 day course for P3e/c and those two were the two strongest opponents against P3e/c. Even the Primavera rep keeps telling me that p3Win is being phased out and I am going to have no choice but to switch to P3e/c. If that truly is the case, then Primavera better make drastic improvements to P3e/c so those of us in construction who are avid P3Win users dont start a revolt.
Take care,
Scott
Member for
21 yearsRE: P3 TO P3 e/c Scheduling problem
Hi Bill,
I agree with you completely, if the tool can do the job why re-invent the wheel. I think a big problem is so-called user friendliness, ie "cater for the folks who can’t think for themselves". I evalued P3e a couple of years ago, and in my opinion, P3 was still the better tool, even though the P3e price a that stage was almost $900-00 less than P3.
As a matter of interest, have you ever used Open Plan V4 (dos)? We were still using it on projects as late 1996, long after the advent of windows. I still believe it was the most flexible planning tools I have used. The trick was that you had to be able to use dbase, which is fairly simple. Even simpler now with the advent of excel and similar spreadsheet programs. The problem was that Welcom software went the same route as Primevera, and started a new product ie Open Plan Professional, which was totally rigid, and which could not do anything near as well as OP v4, and as a result OP virtually disappeared for a few years.
We probably sound like dinosaurs, but at the end of the day we understand our discipline, and do not need these new-fangled gimmicks to improve our planning. Who cares about 16 bit and 32 bit, if you get the right answers?
Regards
Philip
Member for
22 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi Bill,
The reason for tossing out P3WIN if believe was due to its 16 bit architecture and as the technology improved, Primavera had to move to the 32 bit architecture or get Swallowed by other competitors.
Another reson was Portfolio management and not just project management which is the key to success as per recent trends.
I agree to you that we have very experienced users of P3WIN but I am sure they can easily learn or come to terms with P3 E&C in a matter of days. I infact give 2 days crash courses of P3e to experienced users of P3WIN to understand the new windows concepts and terminologies.
Best wishes,
Syed
Member for
22 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi Puneet,
By the way, it is not a book. It is a PDF document created by Primavera Systems, Inc for users who are planning to migrate data from P3 to P3e.
The book which you might be mentioning is also available from Primavera Systems, Inc has a user guide for Engg & Construction users.
I do not deny that P3 3.1 is a good solution but P3 E&C is also being developed and is better than what it used to be.
I am an certified instuctor for all Primavera Products from Primavera Systems, Inc and have provided implementation support to a different clients in different industries for the last 14 years.
Best regards,
Syed, PSP (From AACEI)
Member for
22 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi,
I have sent the same to couple of you through e-mail. It will be great to have your feedback as this will help the users of this thread to know the value and remove misconceptions of migrating from the classical P3 3.1 to Primavera Eng & Constrn or M&T or NPD or IT (Enterprise solution). Current version of the same is 4.1 and 5.0 (which will be released officially shortly) has really some more good features like resource planning and to top it all the UNDO function. I am working with 5.0 Beta version.
Best wishes,
Syed
Member for
20 years 8 monthsRE: P3 TO P3 e/c Scheduling problem
Hi Syed,
Me too!!! Could you please forward the PDF document to my e-mail address. sukumaransubaramaniyan@yahoo.co.uk
Regards.
Member for
20 years 11 monthsRE: P3 TO P3 e/c Scheduling problem
Hi syed,
could you please forward that info on my mail mohdwaseemsaber@yahoo.com.
Cheers!!!!!
waseem saber
Member for
20 years 8 monthsRE: P3 TO P3 e/c Scheduling problem
Bill,
You have confirmed what others have told me. Would you mind expanding on your background and current experience with this subject so I may expand on our side of this debate. Thanks so much for your comments.
Member for
20 years 8 monthsRE: P3 TO P3 e/c Scheduling problem
Hi,
I have a similaar problem. I am using P3 and have 8 projects within 1 master schedule due to the many complex inter-relationships between them. An owners rep I have to report to is wanting me to separate my master schedule into 8 different project files so that when he downloads into P3e/c he can load one project at a time. My projects have codes that clearly identify them individually within my master project. So, what I did to solve the problem is set up a filter for each project within the master schedule and copied each project filter to a separate file. I then made backups of all 8 files for the projects for the owners rep so he can download each one as he needs to into p3e/c. My question is this, isnt there a simpler way that P3 e/c can read this information? Im just not a beliver in setting my master schedule up into the master project - sub-project format that the owner p3 e/c user says is required for him to properly download information.
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi Syed
I read that book ....but that book can not explain all these problems which comes only when you start working on it.
As my schedule is very simple, And when M/s primavera re-schedule the same schedule they find not slipping in dates, and when i re-schedule there comes .. a slppage in dates.
So its only problem setting....of P3 e/c
Regards
Member for
22 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi All,
There is a P3 to P3e migration guide available from Primavera System, Inc. If anyone needs the same kindly send me a e-mail at syed.hasan@cmcs.ae and I would be glad to provide you the same. It is an excellent PDF document which explains all aspects which needs to be taken care of prior to migration of data from P3 to P3e.
Best wishes,
Syed Hasan
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Thanks Ronald
but i tried all the possibilities available in scheduling Advance option.
I sent my schedules to Primavera , and according to them ...there is no change in dates when they schedule it in p3 e/c.
Something really inetersting in settings only.
I will let you know, once i discuss it with Primavera.
but really an interesting feature.
Regards
Member for
22 years 10 monthsRE: P3 TO P3 e/c Scheduling problem
There are quite a few issues in P3ec where there are multiple possible settings where in P3 there is only one (built-in) setting.
The first that comes to mind is the calendar that relationship lags use. You must set the schedule in P3ec to use the ‘Predecessor’s Calendar’ if you want to be compatible with P3.
I assume that when you say that you have checked “everything” that you first compared the dozen or so CPM calculation settings. If not, then you haven’t begun to check for compatibility. Good luck!
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Interruptible Activity setting of P3 may solve the problem but there is no constrain on any activity.
Please explain how to change this setting in p3 or in p3 e/c
No resource... No cost ...so the schedule require no levelling.
I faced the similar problem in p3 e/c 3.5.1 .
In p3 i have only one calendar for all the activities. 5 days a week. Same calendar i am using in p3 e/c.
In admin prferences-> Timeperiod, i changed no of hrs as 8 hrs aday, 40 hrs a week , 200 hrs in a month & 2400.
but again the dates are slipping. even f a change these settings to some new value , the results are same.
Member for
24 years 9 monthsRE: P3 TO P3 e/c Scheduling problem
Frank,
if your resources are restricted then the leveled schedules may be different due to the difference in the scheduling heuristics even when the initial data are the same.
Vladimir
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Hi Frank
I think moving from P3 to P3 e/c explain the features of both P3 & P3 e/c.
Regards
Member for
20 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Thanks to all of you,
Yesterday i talked with Primavera, they were also puzzled. No response from them yet.
My schedule is very simple, 1181 Nos of activities. No resource & No cost... only activities . Type of activities are Task dependents & Milestones.
I check all the calendars, Default calendar & Admin preferences -> Time periods. Everything seems fine.
please help me as primavera is also quite on this.
Regards
Member for
24 years 6 monthsRE: P3 TO P3 e/c Scheduling problem
Ron,
Can I rephrase the question, does anyone have (or know of) a list of the features in P3 and P3e/c that are not supported in the other product that are likely to cause a scheduling differences?
Whilst we can work through the differences as they crop up, a list of things to avoid by both parties will ensure that at least the exchanging of the data is angst free.
I have a list of differences between P3 and SureTrak that I use to set some upfront ground rules to ensure we do not use features that we are unable to replicate in the other product eg. The Interruptible scheduling option is not supported by SureTrak. SureTrak also only recognizes four of P3’s nine autocost rules.
A similar list for P3 and P3e/c would benefit all PPer’s who are in Puneet’s position.
Member for
22 years 10 monthsRE: P3 TO P3 e/c Scheduling problem
Interesting question. Instead of you looking at your schedule to determine what actually did cause the differences, you ask us to list all of the possible issues that you could be experiencing.
For one thing, P3ec does not support the Interruptible Activity setting of P3. If this setting is set to ‘Interruptible’ and you have activities that are constrained by relationships to both their starts and finish, then P3ec would display a difference.
Member for
22 years 7 monthsRE: P3 TO P3 e/c Scheduling problem
Hello Puneet,
I think all the codes(resources,..etc)in P3 should match with the codes in P3e/c., also you have to check for Calendar for Scheduling Relationship Lag(both in P3 and P3 e/c should match like predecessor activity calendar or successor.....).
HTH
Daya