Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2017-08-04 13:43 Permalink is you started now would get is you started now would get one big dump of cost during this update you can manually fix this the work around is to use it from day 1 this is how to edit store period performance To edit stored actual units or cost for a past period If you have already defined the financial period, Select Edit User preference Then select Application - at the bottom under column level- select the financial period for which you want to edit the past period performance of any specific resource assignment-then close Next go to the Activity mode Click the resource tab Right click on resource detail & customize-add columns from "Financial Period Value"- Press ok- Now in the Details window you can edit the past performance actual there. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2017-08-04 13:43 Permalink is you started now would get is you started now would get one big dump of cost during this update you can manually fix this the work around is to use it from day 1 this is how to edit store period performance To edit stored actual units or cost for a past period If you have already defined the financial period, Select Edit User preference Then select Application - at the bottom under column level- select the financial period for which you want to edit the past period performance of any specific resource assignment-then close Next go to the Activity mode Click the resource tab Right click on resource detail & customize-add columns from "Financial Period Value"- Press ok- Now in the Details window you can edit the past performance actual there.
Member for
16 years 3 monthsis you started now would get
is you started now would get one big dump of cost during this update
you can manually fix this
the work around is to use it from day 1
this is how to edit store period performance