I have tasks at the end of my project that occur and finish 6 months out. I have made these tasks INACTIVATE. The active tasks that remain have a finish date this month (approx 6 months prior). Those active tasks have a total slack that evaluates the end dates of my INACTIVATE tasks. I don't want MSProject to use the dates of the INACTIVATE tasks.
Member for
13 years 3 monthsHi,I have tasks at the end of
Hi,
I have tasks at the end of my project that occur and finish 6 months out. I have made these tasks INACTIVATE. The active tasks that remain have a finish date this month (approx 6 months prior). Those active tasks have a total slack that evaluates the end dates of my INACTIVATE tasks. I don't want MSProject to use the dates of the INACTIVATE tasks.
Member for
17 years 9 monthsErnie,what do you mean
Ernie,
what do you mean exactly, can you clarify?
Regards.