"Composite" Timescale in MSP2010

Member for

22 years 11 months

Thanks for confirming Alexandre.

Member for

22 years 9 months

Tony,

unfortunately not; it is not possible to have such a composite timescale in MSP, whatever the version is; however it is easy to swith from quartely to monthly to daily by clicking on the Zoom In/Zomm Out magnifiers icons.

Alexandre