when you update the project with the option "Reschedule uncompleted work after the status date" (freely translated from French), MS Project assigns a Start No Earlier Than constraint to the unstarted activities, and a Resume Date to the activities which had started before the update and are suspended
there is no way to refuse the constraint, or the activity will be scheduled back in the past
Member for
22 years 9 monthsJames,when you update the
James,
when you update the project with the option "Reschedule uncompleted work after the status date" (freely translated from French), MS Project assigns a Start No Earlier Than constraint to the unstarted activities, and a Resume Date to the activities which had started before the update and are suspended
there is no way to refuse the constraint, or the activity will be scheduled back in the past
Alexandre