Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2011-12-03 09:43 Permalink Hello,such filter already Hello, such filter already exists in MS Project, all versions: go to Project, Filter for, More filters then select "Should start / finish before" Alexandre Note: as I am working with MSP in French, the filter name might be slightly different. Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2011-12-03 09:43 Permalink Hello,such filter already Hello, such filter already exists in MS Project, all versions: go to Project, Filter for, More filters then select "Should start / finish before" Alexandre Note: as I am working with MSP in French, the filter name might be slightly different.
Member for
22 years 9 monthsHello,such filter already
Hello,
such filter already exists in MS Project, all versions: go to Project, Filter for, More filters
then select "Should start / finish before"
Alexandre
Note: as I am working with MSP in French, the filter name might be slightly different.