The standard function: "ProjDateDiff( date1, date2, calendar )" is what you are looking for.
This will give you the working days (expressed in minutes in from the top of my head) between the two dates, according to the specified task calendar. (not the resource calendar)
Member for
17 years 6 monthsRE: Calculating % on track
Awesome. Thank you!
Member for
20 years 7 monthsRE: Calculating % on track
Jeff,
The standard function: "ProjDateDiff( date1, date2, calendar )" is what you are looking for.
This will give you the working days (expressed in minutes in from the top of my head) between the two dates, according to the specified task calendar. (not the resource calendar)
H.T.H.