P3e No of activities

Member for

18 years 9 months

Hi David

You adressed a very important item: All items have to be discussed before the project starts. Especially for a turnaround. ALL reports, all discussions on mailing lists must be done before. Responsibilities for progress reporting clear. Regulations, e.g. pay contractors on reported and confirmed progress only as well.

During the project you as a terrier hunting for progress data.

P3e’s publish feature is very helpful.

Henry don’t be afraid on the number of activities!

Dieter


Member for

18 years 3 months

Henry,

I just finished a turnaround with just over 6000 activities. It was not the schedule that was hard to keep up with. My client had just gotten P3e on there site and someone had commited every report they could think of to be delivered during the turnaround. Each report had to be published, printed to pdf and emailed to different managers. There were several layouts that had to be published, printed to pdf and mailed to managers. I was also required to attend 2 meetings a day. Progress was done twice a day.



You see what I’m getting at? I am now building a schedule that is expected to reach 25,000 activities. I have a young scheduler that will help with updates.



I found out that the schedule was the easy part, it was all the other things that kept me behind. This time I am going to try and control the number of reports and layouts that I run each shift. (I had no control before.) My plans are to publish the project and or the reports and send everyone a link to the folder that it is published to.



Just don’t forget all the other things that a scheduler may be asked to do during the turnaround or project you have coming up.



And Again Good Luck!



David

Member for

18 years 9 months

Hi Henry

For P3e or P3 it is no problem to handle. It’s up to you to well structure: Mainly WBS and Activity Codes to keep an overview.

My biggest project was about 190000 activities (1,5 years of planning, daily reporting and bi-directional transfer with SAP during life-time). Project ended the scheduled day. Due to SAP we "over-structured".

Good luck!

Dieter

Member for

18 years 2 months

my last was 25000, built and updated daily by 2 of us



Takes 2 people about 1 1/2 hours a day to do the update (roughly 6-800 activities per day) once progress has been collected.



so 3-4000 shouldn’t be a major challenge.



however, think about your progress gathering system. This is what takes the time if it’s not thought out fully. Data entry is quick once the data is there.

Member for

18 years 5 months

My last project: 48000 activities, done with the help of a junior (Junior used for updates only)