Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Thu, 2007-07-05 03:25 Permalink RE: Constriant Why not link in a finish milestone at the end of your activities and use a Finish On or Before constraint on that milestone? This is the usual manner of representing compeltion dates. Log in or register to post comments
Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Thu, 2007-07-05 03:25 Permalink RE: Constriant Why not link in a finish milestone at the end of your activities and use a Finish On or Before constraint on that milestone? This is the usual manner of representing compeltion dates.
Member for
20 years 6 monthsRE: Constriant
Why not link in a finish milestone at the end of your activities and use a Finish On or Before constraint on that milestone? This is the usual manner of representing compeltion dates.