It is ussally, if not never, is a scheulders/planner job to develop a schedule without any interation with the entire team. You will attend a few meetings and only then the things will start openning up at you. Even your eamil clearly decribes the WBS for the project i.e starting from feasibility study , engineering , formation and award of EPC contracts......Just develop that and then when you are attending the meetings, fish for the activty deceriptions and load them in the appopriate WBS.
I can guide you about the buffers, soft and hard logic that the activties will be having for such a linear project, however i think that it is too early for that. Thanks.
Member for
20 years 6 monthsRE: REFERENCE PLANNING FOR EPC PIPELINE PROJECTS
Sanjeev,
It is ussally, if not never, is a scheulders/planner job to develop a schedule without any interation with the entire team. You will attend a few meetings and only then the things will start openning up at you. Even your eamil clearly decribes the WBS for the project i.e starting from feasibility study , engineering , formation and award of EPC contracts......Just develop that and then when you are attending the meetings, fish for the activty deceriptions and load them in the appopriate WBS.
I can guide you about the buffers, soft and hard logic that the activties will be having for such a linear project, however i think that it is too early for that. Thanks.
Regards
Rashid