Current progress against baseline?

Member for

22 years 9 months

Not sure this is what you ask for but you can use

"View"

"Progress Spotlight"



This will give you a progress line for with the data date line show whether the activity is ahead of behine schedule



HTH



Alex

Member for

24 years 5 months

I am struggling with same problem.

I can display bars for baseline OK

When I apply progress bars, progress is shown from actual start not baseline start?





In P3 %progress was shown from Target start date?

Member for

22 years 3 months

No offence taken. I’ve been using this software for a few years now and always find something else to learn and there’s sometimes half a dozen ways to do it.



Cheers

Member for

20 years 10 months

Kevin, funny, now I read it again, your right, sorry no offence intended.

I just haven’t seen baseline progress done yet in P3e.

Member for

22 years 3 months

...define a new set of bars to reflect original baseline and report progress against these...



Which is what I was suggesting anyway, just said it a different way.

Member for

20 years 10 months

There is no option to do this. Although it should be possible to define a new set of bars to reflect original baseline and report progress against these. It should be ...

Member for

22 years 3 months

Not sure that I fully understand what you need but you might need to play with some new bars and create one that uses the Plan Bar for the timescale and have the % Complete displayed on this bar.