To show and analyse dependancies between 2 projects I often use a "Inter-Project Links" project, where I work with the Primary Constraint.



Then, as soon as both projects are updated, I open both of these project and the "Inter-Project Links" one, I schedule.

Then I analyse if all dates are OK with the "Trace Logic" buttom in Activity view (that I have customize).




Member for

18 years 10 months

Ha! I am the Chris at Sizewell! I will send you an internal e-mail tomorrow; however after speaking to people it appears we will not need this function however it would still be useful to understand how it works so I’d appreciate a look at the presentation!



Thanks!

Member for

23 years 11 months

Send me an email and I will give you a copy of a Powerpoint presentation.



Regards



Dave



PS if you are the Chris at Sizewell contact me on the Internal email system !!!!!

Member for

18 years 10 months

That’s brilliant, the gateway WBS sounds very good, how do I construct one of them. I searched the help file, but can’t find any results.



Thanks in advance



Chris

Member for

23 years 11 months

Three options that I use are:



1 add a suffix to the activity ID to show dependency and delivery type activities



2 use an activity code to identify dependency and delivery inter project relationships



3 create a gateway WBS and manage all inter project links via the gateway



Hope this helps



Regards



Dave