Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 6 months Submitted by Chris Radecki on Tue, 2006-12-12 01:56 Permalink RE: Importing P3 projects - activity codes On the question, a RAG way be to use xerFileParser&Builder.xls from P3 POINT site. Setup projects with activity codes and dummy activity codes value, export them to xer, use the above xls to split the activity codes Cannot remember how to export activity codes from P3, but sure there is a way. Copy to the xerFileParser&Builder.xls and convert to xer and import. Sorry that it is RAG. Member for 20 years 6 months Member for 20 years 6 months Submitted by Chris Radecki on Tue, 2006-12-12 01:43 Permalink RE: Importing P3 projects - activity codes Take care with activity codes at EPS or Project level. I am not too cluey on importing them, but.... There is a glitch with Puge Deletes in 5sp1/0 where EPS or Project level activity codes can bedeleted from the activity ID assignation. I like the codes at EPS/Project level - just have to accept that have to export/backup the acivity assignation, and reimport when they are lost. Maybe SP2 solves this problem; not using purge deletes seems also to work at present ;-) Member for 18 years 11 months Member for 18 years 11 months Submitted by Sufian Malik on Mon, 2006-12-11 08:04 Permalink RE: Importing P3 projects - activity codes Additonal information: When going through the import : 1)If you select combine sub projects then the project codes are added in the activity codes dictionary at a project level 2)If you select create separate projects then they should be added at a global level. Member for 18 years 11 months Member for 18 years 11 months Submitted by Sufian Malik on Mon, 2006-12-11 07:28 Permalink RE: Importing P3 projects - activity codes Hi there When importing a project, activity codes are added in the project dictionary of activity codes Regards Sufian Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Chris Radecki on Tue, 2006-12-12 01:56 Permalink RE: Importing P3 projects - activity codes On the question, a RAG way be to use xerFileParser&Builder.xls from P3 POINT site. Setup projects with activity codes and dummy activity codes value, export them to xer, use the above xls to split the activity codes Cannot remember how to export activity codes from P3, but sure there is a way. Copy to the xerFileParser&Builder.xls and convert to xer and import. Sorry that it is RAG.
Member for 20 years 6 months Member for 20 years 6 months Submitted by Chris Radecki on Tue, 2006-12-12 01:43 Permalink RE: Importing P3 projects - activity codes Take care with activity codes at EPS or Project level. I am not too cluey on importing them, but.... There is a glitch with Puge Deletes in 5sp1/0 where EPS or Project level activity codes can bedeleted from the activity ID assignation. I like the codes at EPS/Project level - just have to accept that have to export/backup the acivity assignation, and reimport when they are lost. Maybe SP2 solves this problem; not using purge deletes seems also to work at present ;-)
Member for 18 years 11 months Member for 18 years 11 months Submitted by Sufian Malik on Mon, 2006-12-11 08:04 Permalink RE: Importing P3 projects - activity codes Additonal information: When going through the import : 1)If you select combine sub projects then the project codes are added in the activity codes dictionary at a project level 2)If you select create separate projects then they should be added at a global level.
Member for 18 years 11 months Member for 18 years 11 months Submitted by Sufian Malik on Mon, 2006-12-11 07:28 Permalink RE: Importing P3 projects - activity codes Hi there When importing a project, activity codes are added in the project dictionary of activity codes Regards Sufian
Member for
20 years 6 monthsRE: Importing P3 projects - activity codes
On the question, a RAG way be to use xerFileParser&Builder.xls from P3 POINT site.
Setup projects with activity codes and dummy activity codes value, export them to xer, use the above xls to split the activity codes
Cannot remember how to export activity codes from P3, but sure there is a way.
Copy to the xerFileParser&Builder.xls and convert to xer and import.
Sorry that it is RAG.
Member for
20 years 6 monthsRE: Importing P3 projects - activity codes
Take care with activity codes at EPS or Project level. I am not too cluey on importing them, but....
There is a glitch with Puge Deletes in 5sp1/0 where EPS or Project level activity codes can bedeleted from the activity ID assignation.
I like the codes at EPS/Project level - just have to accept that have to export/backup the acivity assignation, and reimport when they are lost.
Maybe SP2 solves this problem; not using purge deletes seems also to work at present ;-)
Member for
18 years 11 monthsRE: Importing P3 projects - activity codes
Additonal information:
When going through the import :
1)If you select combine sub projects then the project codes are added in the activity codes dictionary at a project level
2)If you select create separate projects then they should be added at a global level.
Member for
18 years 11 monthsRE: Importing P3 projects - activity codes
Hi there
When importing a project, activity codes are added in the project dictionary of activity codes
Regards
Sufian