BCWS at Task Level not calculating

Member for

19 years 5 months

Colleen,



Have set the status-date, via Project>Project Information?



James.

Member for

21 years 8 months

Work around



Buy a program that works properly, get yourself trained in Earned Value not just how to use MSProject



Distrust absolutely any cost calculations done by MSProject



I will train you just email me PMwork1@bigpond.net.au



Regards



tom