I am creating a revised target program. I have a number of activities which start dates are pushing out past the data date or will not fix to the date I assign. These activities have no constraints and no relationships! Something is driving them but it is unclear what. The start and finish dates show a star symbol even though no constraints or relationships are assigned? Has anyone come across this before?
P6 start & finishes fixed
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
There are other ways to clear the external links, but Frederick method is quick and simple.
Just checked my External links and your correct.
Frederic your a legend, thank you very much.
Its always somthing simple....
Bill,
Try to open up the Predecessor or Relationship Column.
Bill,
I faced the same issue: Star symbol on finish dates while no constraint was assigned.
It was coming from field "External finish date". Indeed, when some inter-project relationship are lost, P6 is constraining Early/late dates. Like this, it is artificially keeping time logic.
To recover a proper schedule, add column "External finish date" and manually remove date within cells.
Launch calculation, everything should be OK,
regards
Bill,
Check the Planned Start dta and the Data Date.
Kannan
@#)