How to choise the général method of the planning (Fixed unit or Fixed duration or physical ... Top down method ...)

 

Good morning,

We have a project ( Construction of LNG train in Balhaf for example) with many Sub contractors ,....,many plannings,.

How to proceed to prépare the Master planning ,what are the steps to follow...

Which calculation méthod to use ,the type of the activities,....

 

Thank you

 

W
walid Lahiani 👤 Member for 15 years 7 months

Thank you for your explication,

 

"If we don't know the method of calculation ,we can not work properly"

It's like the foundation of the building

 

S
Shazia khan 👤 Member for 18 years 1 month

first you determine your self , how you want to update your project,

is that schedule have fixed resource or fixed duration.

best practice is herego

1- duration type       ===== fixed duration and unit

 

2-Percent type       ====== Duration for engineering & procurement activity,

                                           Physical for construction activity.

 

3-Activity type ==========  Task Dependent ,  ( for mile stone depends start MS or Finish MS )

 

with this setting you need to update your schedule based on your physical judgement or progress measurement sheet,

update with Phy %  value , remaining duration,  start date , etc,

resource update actual unit and remaining units..

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts