Impact Of Calc Start-To-Start Lag From Actual Start
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Khuong has the correct explaination
Hi there,
I wrote an article to explain these options.
Kindly read it here https://doduykhuong.com/2020/01/26/primavera-p6-schedule-options-calculate-start-to-start-lag-from/
Regards,
Khuong
Gentleman,
Can you expalin the question and answer as well please.
thanks
AK
A lot depends on the project status and also on the agressiveness of the Planning Engr.
I would prefer to have this calculated using Early Start, as this will give more conservative Schedule but again this will also lead to delay in start of successor.
Choice is yours!!